27. Model Contract — Dispute Settlement — Resolution of Discrepancies
27.1. In matters pertaining to proposed and/or approved IRB Transactions, in circumstances where the IRB Authority and the Contractor fail to agree after negotiating in good faith, then the decision of the IRB Authority will prevail.
27.2. In the event that the Contractor fails to agree to the decision rendered by the IRB Authority, then the Contractor may, within twenty-eight (28) calendar days of receipt of Canada's decision, submit a request to the Contracting Authority, for reconsideration of the matter by the IRB Authority. Such a request shall fully describe the issue, all relevant factors and the reasons for the Contractor's disagreement. Industry Canada will, within twenty-eight (28) calendar days of receipt of the request, issue the final determination detailing the reasons for the decision.