Bart College
Project: Conversion of part of the garage to a classroom, air conditioning and installation of whiteboards
Total Project Cost:
$232,900
Total KIP Funding:
$116,450
Status of Project: Substantially completed
Project Description
This project involves converting part of the college warehouse into classrooms and production studios for students. The work also includes installation of interactive boards in some rooms and upgrading of the classroom air conditioning system.
Primary Areas of Benefit
- Expands or enhances the utility of training space: The project makes room for 35 additional students in the DEC program in 3D animation and image synthesizing.
- Improves energy efficiency: Construction work in the garage leads to energy savings through superior insulation.
- Date modified: